Summary

Public Works told the board that South Avenue sewer work is being filled, chlorinated and tested and that the town received a $1.1 million state local bridge grant for the Lakeview culvert (work to begin April 2027). Staff also reviewed recent storm flooding, cleanup response, and plans for trail repairs and bids.

Public Works provided a lengthy update on Aug. 4 covering South Avenue construction, recent storm flooding, and successful grant awards.

Staff said Aquarian finished pipe installation on South Avenue and crews are filling, chlorinating and testing lines; if tests pass the town will begin paving and hopes to shift contractor schedules to finish much paving before school starts. "They're filling, chlorinating, and starting to test," the Public Works presenter said, adding that testing is a two‑ to three‑day process and a single failing joint could require excavation.

In other major developments, the town won $1.1 million from Connecticut's local bridge program for the Lakeview culvert project, which staff said is slated to begin in April 2027 and will require a full seasonal closure. Officials also noted a related $350,000 community connectivity grant that will pay for a sidewalk from Lakeview to Maine Avenue at no cost to the town.

Public Works reviewed extensive cleanup after a heavy storm that caused flooding across multiple municipal buildings and parks. Staff described rapid emergency response, ongoing restoration work with a remediation contractor and planned trail repair bids; they said flood insurance is being processed and one aggregated claim approach helps address multiple buildings but the town's flood policy retains a $50,000 deductible.

Board members asked about schedules and next meeting updates; staff said they expect more detailed testing and paving schedule information by the next board meeting.