Poulsbo trims public-works facility design, targets roughly $20 million price tag

Poulsbo City Council · June 10, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

After value engineering, staff presented an alternate maintenance-facility design that reduces covered space and aims to lower the 2026 cost estimate from about $25.5 million to roughly $20 million, with design completion this year and construction planned to start in 2027.

Public Works Director Diane Linnaeus told the council that Helix Design Group’s initial schematic for a new maintenance facility—which originally laid out roughly 33,000 square feet of covered space—produced a 2026 cost estimate of about $25.5 million. After value engineering and adjustments to site grading and building footprints, staff said an alternate design would provide roughly 28,000 square feet of covered roof space and reduce costs by about $5.5 million.

"We reduced it by approximately $5,000,000," Linnaeus said when describing the value-engineered alternative and tradeoffs the team evaluated to avoid extensive retaining walls while still meeting functional needs. She said the team will finalize value engineering in June/early July, present a formal recommendation to council in July, and submit a site-development application so design can finish this year with advertisement for construction in early 2027.

Council members asked whether moving buildings inward to save on retaining walls would limit future expansion or parking. Staff responded that the alternative is intended as a 20-year plan and noted city-owned property near the admin building could provide additional storage if needed. Staff also said outsourcing solid-waste services and enterprise-fund contributions factor into the finance plan for the project.