Washington County receives $29,409.86 credit on Cove Road Bridge change order
Summary
Road and Bridge Supervisor Jerod Odoms told commissioners that Change Order #5 for the Cove Road Bridge project reflects a $29,409.86 credit after inspection discrepancies with material specification thresholds; the Board approved the credit.
Get email alerts on the Infrastructure Bridge topic
No spam. Unsubscribe anytime.
Jerod Odoms, Road and Bridge and Solid Waste Supervisor, presented Change Order #5 for the Cove Road Bridge project and explained it represented a credit to the county due to inspection findings. Odoms said the materials performed adequately for the bridge but did not meet upper contractual specification thresholds, which triggered an adjustment against the contractor's payment.
"the change order reflects a credit to the county resulting from inspection failures related to granular base and asphalt materials," Odoms told the Board. The commissioners voted to approve Change Order #5, registering a $29,409.86 reduction in the county's contract payment obligations for the project. The Board recorded the motion as carried; no further fiscal action was recorded at the meeting.