Council sets criteria for façade change orders: contingency or prepaid requirement
Summary
After extended debate over risk to the city and small-business impacts, Indianola's council directed staff to bring CDBG-funded façade change orders forward only when covered by contingency funds or when property owners are current on invoices and prepay the change order amount.
Get email alerts on the Grants topic
No spam. Unsubscribe anytime.
City staff told the council on Aug. 3 that renovation work tied to a Community Development Block Grant (CDBG) has produced multiple change orders, including one large request of roughly $67,000. Staff outlined three options for processing change orders: require prepayment (hold funds in escrow), approve only for owners current on invoices, or bring all change orders forward regardless of payment.
Jake (city staff) framed the issue as a choice of risk tolerance: "The most conservative approach that limits the city's liability to the greatest extent is to require the property owners to deposit the funds for the change order to the city in advance of it bringing forward for council consideration." Council members debated whether the city should act as an interest-free lender to small businesses or require owners to have funds in hand before construction moves forward.
After extensive discussion about legal remedies and the burden on small businesses, the council directed staff to present future change-order agenda items only if the work could be covered by contingency funds or if the property owner was current on invoices and had pre-funded (or brought funds) for the change order. Council also authorized a special meeting to consider change orders that meet those criteria so work can proceed without delay. "I'll approve every change order that comes through that is paid for upfront," one council member said during the debate.
Staff said four change orders are expected to be covered by contingency and one large change order (about $67,000) remains in question; staff will communicate the adopted parameters to property owners and contractors prior to the next agenda cycle.