Transportation staff said the Eustic Corridor project will widen about 1.7 miles of Eustic Road to a five‑lane urban section with median, concrete intersections, new traffic signal and protected U‑turn designs (RCUT/ARCT), multiuse pathways and improved utilities; completion is projected in July 2027.
Get email alerts on the Transportation topic
No spam. Unsubscribe anytime.
Crystal Craig, the city’s director of transportation, presented the Eustic Corridor update and described a roughly 1.7‑mile widening from east of Phyllis Canal to State Highway 16 that will convert the roadway from a rural two‑lane to an urban five‑lane section with a center median, improved lighting, underground utilities and 10‑foot concrete side paths to separate cyclists and pedestrians from traffic.
Craig said the corridor study projects traffic on Eustic could rise dramatically with the new state highway connection — "projected to increase traffic on Eustic Road by nearly 632%" — and that the design includes restricted crossing U‑turn (RCUT or "loon") intersections and signalized approaches at key nodes to improve safety. She said the city and contractor will use a phased approach to keep at least one lane open in each direction during construction, and that contractors are working to avoid blocking business access; staff will follow up directly with Club Storage Condos about a concrete curb that owners said blocks their entry.
Why it matters: This project modifies access patterns for businesses and residents along Eustic Road, adds multimodal infrastructure, and has a multi‑year construction timeline that requires coordination to minimize disruptions.
What comes next: Craig said interactive maps and renderings are available on the project website and staff will continue outreach; final completion is currently projected for July 2027, with sections opening incrementally as they finish.