Parks planning administrator gives multi-site capital-improvement update; senior center target set for October

Parks and Recreation Advisory Board · June 3, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Mark Eller reported construction progress at multiple parks projects: senior center paving and interior work are underway with an expected substantial completion in October (a speaker referenced "October 20"); asbestos abatement at Lou Health Park is expected to finish this week and interior salvage will follow.

Mark Eller, Parks Planning Administrator, briefed the board on several capital-improvement projects across the city.

Eller said the downtown senior center—s exterior and interior work is progressing, with site paving (pedestrian and vehicular) underway, followed by irrigation, landscaping and lighting. During the exchange staff noted a target of "October 20" for substantial completion and reminded members weather can affect timing.

On Lou Health Park, Eller said the rec center—s asbestos abatement "is expected to be completed by, this Friday this week," after which interior salvage of structural members and some flooring will begin; the abatement area is sealed and being protected. Eller also described playground installations, rubber surfacing schedule and the need for utilities coordination on trail work.