Selectboard confirms MERP energy upgrade timeline; HVAC work to begin in July
Summary
The Board received a MERP contractor update on energy upgrades at the Town Office: electrical staging will precede HVAC work in July, spray-foam insulation will require temporary vacancy, and the grant sets a December 31 completion deadline though work is expected to finish earlier.
Get email alerts on the Energy Upgrades topic
No spam. Unsubscribe anytime.
Chair Susan Culp reported on an agreed work plan and timeline with MERP contractor Bill Graves for energy upgrades at the Town Office, saying HVAC work—the most disruptive phase—will begin in July after electrical staging. Culp said spray foam insulation will require temporarily vacating the building and that efforts will be made to minimize disruption for town staff and the Post Office.
Culp noted the grant sets a project completion deadline of December 31 but said work is expected to finish this fall; the town attorney prepared a revised contract. The Board did not vote on the contract at the meeting but recorded that coordination with the contractor and preparation of the revised contract are complete.