County approves supplemental design work for US 30 project, federal-aid agreement for Bridge D-11, and orders polymer-coated pipe for culvert replacement
Summary
The Board approved a supplemental agreement with Snyder & Associates for additional design on the US 30/Binford Ave/245th St project, accepted a federal-aid agreement for Bridge D-11 replacement, and County Engineer reported purchase of a polymer-coated metal pipe for a culvert on 280th Street.
Get email alerts on the Transportation topic
No spam. Unsubscribe anytime.
County Engineer Paul Geilenfeldt presented and the Board approved Supplemental Agreement No. 01 with Snyder & Associates for additional design services related to the US 30, Binford Avenue, and 245th Street improvement project; Geilenfeldt said the supplemental work covers design modifications and the project remains on schedule for an October letting with a potential early start of April 1, 2027.
The Board also approved the Federal-Aid Agreement for County Highway Bridge Program Project BROS-C064(152)-8J-64 for replacement of Bridge D-11 on 120th Street over Minerva Creek to secure federal funding for the replacement. In a public update, Geilenfeldt reported a culvert failure on 280th Street (E63) and that the County elected to purchase a polymer-coated metal pipe with an anticipated 100-year service life; installation was expected the following week with temporary rock surfacing followed by a hot-mix asphalt patch.