The board approved a contract to modernize the Green River Courthouse elevator and authorized the chairman to sign; Public Works described a full modernization to meet current standards and upgrades to accessibility communications.
Get email alerts on the Facilities topic
No spam. Unsubscribe anytime.
Sweetwater County commissioners approved the Green River Courthouse elevator modernization project and authorized a contract with Kone, the county’s elevator maintenance provider.
Public Works Director Gene Legurski said the project will fully modernize the elevator — removing original 1964 control equipment, replacing drive and hydraulic systems, updating door systems and adding accessibility features such as a visual/LED communication module for the deaf and hard-of-hearing. Legurski told the board the project is included in the capital budget and estimated a roughly six-week construction window once components are on order.
During the meeting Legurski stated the engineer’s estimate was lower than bid results but said the board had transferred money from underrun capital projects to cover the increase. The board moved, seconded and approved the contract by voice vote.
Note on transcript discrepancy: Legurski announced a project sum earlier in his presentation; the clerk’s motion text later in the transcript contains a typographic/transcription error showing an implausibly large figure. The county’s presentation described a budgeted modernization; the board approved the project and authorized the chairman to sign contract documents.