Impact theater renovation budgeted at just over $10M; demo complete, mid-November reopening targeted
Summary
Presenters told the Visit McKinney board that the Impact (old courthouse) renovation carries a budget just over $10 million — about $8.5M for construction, $1.5M for professional services and $500K for furniture and fixtures — with demolition finished and a mid-November 2026 completion target; seating will increase to roughly 415–417.
Get email alerts on the Historic Renovation topic
No spam. Unsubscribe anytime.
A presenter on the Impact (old courthouse) renovation told the Visit McKinney board that work is underway under Texas Historic Commission oversight and that demolition is now complete.
"The overall project budget is, just over 10,000,000, you know, 8.5 for the construction and then about and then about 1.5 for, or 1,000,000 for professional services and other engineering services and then 500 for furniture, fixtures and equipment," the presenter said, describing the funding breakdown. The presentation said interior upgrades will include theater-technology improvements, a permanent stage, acoustics work, more comfortable seating and restored architectural finishes.
The presenter said the project is on target for completion by mid-November 2026. Seating capacity will increase to about 415–417 when renovations are finished; no formal reopening celebration date has been set, though staff indicated a larger celebration is possible in early 2027.