Committee recommends $19,816 chiller compressor replacement after AHU-1 failure
Hononegah Community High School Finance Committee · October 15, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.
Summary
Staff reported the AHU-1 chiller compressor (about seven years old) failed; Ceroni Piping quoted $19,816.00 for replacement and the committee recommended Board approval.
Get email alerts on the Facilities Maintenance topic
No spam. Unsubscribe anytime.
Staff told the committee that the compressor serving AHU-1, which is roughly seven years old, failed and requires replacement.
Mike Dugan reported the failure and noted Ceroni Piping Company submitted a replacement quote for $19,816.00. The committee recommended the Board approve the expenditure and forward the vendor quote for Board action.
No committee vote totals were recorded in the transcript; the item was advanced as a recommendation to the Board.