Staff reports schedule for classroom plaster repairs, hallway retiling and field‑house work
Summary
Facilities staff updated the committee on completion of plaster/ceiling repairs in 10 classrooms, retiling of the 1500 hallway over winter break with the 'H' logo, and field house track, gas valve, and smoke/heat detector work scheduled for Dec. 20.
Get email alerts on the Facilities Repairs topic
No spam. Unsubscribe anytime.
Sean Huffstutler updated the committee on ongoing facilities work. Room 2417 has been completed, Room 2415 is scheduled for completion in the second week after the break, and staff plan to finish one classroom per week until all required plaster and ceiling repairs are done.
Huffstutler also said crews will retile the 1500 hallway with the district 'H' logo over the winter break. Field house track work is scheduled for Dec. 20, during which gas shut-off valves will be installed and the smoke/heat detector project will be completed.