County approves $34,724.96 deduction for late chip-seal work on Lehi 14
Summary
Commissioners approved a change order deducting $34,724.96 in liquidated damages from the Lehi 14 chip seal contractor's bill and authorized the chairman to sign the order.
Get email alerts on the Roads Contracts topic
No spam. Unsubscribe anytime.
County staff presented a change order for the Lehi 14 chip-seal project that reflects liquidated damages owed by the contractor for delays. The county's net deduction in the contractor's favor amounts to $34,724.96; staff described the amount as "in our favor" and requested the chairman's signature on the change order.
The board moved, seconded and approved the chairman's signature on the change order by voice vote. Staff said the deduction represents liquidated damages for work that was late and that the county had already communicated the amount to the contractor; no additional conditions or appeals were recorded during the meeting.
Commissioners also received updates on other road projects, including Homestake road improvements and pending easement discussions with landowners.