Commission awards $35,673.90 courthouse concrete contract and authorizes glass work up to $9,845
Summary
Facilities Director Keith Coleman presented bids for concrete and glass work around the courthouse; the commission awarded ASC Construction $35,673.90 for concrete and authorized Coleman to accept a glass bid not to exceed $9,845.
Get email alerts on the Facilities Maintenance topic
No spam. Unsubscribe anytime.
Facilities Director Keith Coleman presented bids for concrete repairs around the courthouse and a separate glass removal/replacement scope. He reported some work will require glass removal and had received a vendor bid; respondents to bid requests were limited.
The commission approved ASC Construction's $35,673.90 bid for concrete and gave Coleman authority to accept a glass bid not to exceed $9,845. Coleman confirmed there are sufficient funds in the Courthouse Improvement Fund to cover the work.