County selects Option 1 for 464th Avenue safety project; construction slated for 2028
Summary
Highway Superintendent Brian Gustad told commissioners the county received a safety grant after fatalities at the 464th Avenue and 220th Street intersection and recommended Option 1 for right-of-way layout; the board agreed by consensus and Gustad said construction would occur in 2028.
Get email alerts on the Transportation topic
No spam. Unsubscribe anytime.
Highway Superintendent Brian Gustad briefed the Brookings County Commission on May 19 that the county secured a safety grant after fatalities at the 464th Avenue and 220th Street intersection and presented right-of-way layout options produced by the Department of Transportation.
Gustad said the intersection sits low into wetlands and that procurement of wetland mitigation credits will be necessary. He recommended Option 1 for the right-of-way layout; by consensus the board agreed to move forward with Option 1 and Gustad said construction is scheduled for 2028.
The board also noted a bid opening for two structures will occur June 16 at 2:30 p.m. in the Community Room next to the Chambers. The county will coordinate DOT options, wetland mitigation planning and subsequent contracting ahead of the 2028 construction window.