Edisto Beach approves $31,613.25 change order for final Town Hall site and electrical work

Town of Edisto Beach Town Council · June 11, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council approved Change Order No. 009 with Monteith Construction Corp. for $31,613.25 to cover additional site and electrical modifications at the new Town Hall/EOC; contractors are completing punch-list items.

Council approved Change Order No. 009 with Monteith Construction Corp. for $31,613.25 on June 11, 2026, to cover additional site and electrical modifications identified after completion of the new Town Hall and Emergency Operations Center. Council Member Robert Renner moved the change order and Council Member Jay Watts seconded; the motion passed unanimously.

Town staff reported contractors are completing remaining punch-list items and that the building represents an investment the community can take pride in. The change order covers minor drainage and electrical adjustments needed after initial completion sign-offs.