Architects outline 3–4 year schedule if Middlesex approves MHS project
Summary
Moseley gave a projected schedule that includes 6–8 weeks for design partner selection, 8–10 months for design and production, 2–3 months for bidding, and 24–28 months for construction, with Option 6 offering phasing that may avoid portable classrooms.
Get email alerts on the Procurement Timeline topic
No spam. Unsubscribe anytime.
At the July 22 joint session, architects presented a high-level procurement and construction schedule for the proposed MHS work.
Stephen Halsey said the sequence following a Board "thumbs up" would begin with design partner selection (6–8 weeks), followed by design and production (8–10 months), bidding and award (2–3 months), and construction lasting 24–28 months. He noted Option 6’s ability to build a new classroom wing first to serve as "swing space," which could reduce or eliminate the need for portable classrooms during construction.
Board members did not accept or reject a schedule in this meeting and asked for further financial detail before authorizing advancement to procurement activities. The timeframe given is a planning estimate tied to the chosen option and to market conditions and bidding outcomes.