Trustees authorize loan documents for Phase II water meters; project estimated at $300,000
Summary
Benton & Associates told the Board 238 water meters need replacement at $800 apiece (about $250,000) plus $30,000 for engineering, bringing the estimated Phase II water project cost to $300,000; the Board authorized President Danner to sign loan documents.
Get email alerts on the Water Infrastructure topic
No spam. Unsubscribe anytime.
The Board authorized President Staci Danner to sign loan documents for Phase II water improvements after Benton & Associates reported a plan to replace 238 water meters at an estimated unit cost of $800, resulting in roughly $250,000 for meters and $30,000 in engineering for a $300,000 total estimate.
Trustee Jones moved to authorize President Danner to execute the loan documents and Trustee Thompson seconded; the motion carried. Benton & Associates will gather detailed prices and information on meter replacement for next steps.