Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Water Infrastructure topic

No spam. Unsubscribe anytime.

Trustees authorize loan documents for Phase II water meters; project estimated at $300,000

Village of Industry Board of Trustees · January 2, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Benton & Associates told the Board 238 water meters need replacement at $800 apiece (about $250,000) plus $30,000 for engineering, bringing the estimated Phase II water project cost to $300,000; the Board authorized President Danner to sign loan documents.

The Board authorized President Staci Danner to sign loan documents for Phase II water improvements after Benton & Associates reported a plan to replace 238 water meters at an estimated unit cost of $800, resulting in roughly $250,000 for meters and $30,000 in engineering for a $300,000 total estimate.

Trustee Jones moved to authorize President Danner to execute the loan documents and Trustee Thompson seconded; the motion carried. Benton & Associates will gather detailed prices and information on meter replacement for next steps.