Riverside Drive flap gate box design advanced; approvals needed from flood control and Army Corps
Summary
Staff reported that the flap gate box design has been priced and is awaiting reviews by the local flood control district and the U.S. Army Corps of Engineers; INDOT must approve a change order before the contractor can order the precast box.
Get email alerts on the Flood Control topic
No spam. Unsubscribe anytime.
Staff updated the commission on Riverside Drive flood-control work, saying the flap gate box design has been priced and the flap gate itself is on a roughly 26-week order. Staff emphasized the box can be constructed before the flap gate arrives but said approvals are needed from local flood control and the U.S. Army Corps of Engineers before the contractor can order the precast box.
The project team explained the construction sequence: the contractor will precast the concrete box off-site, deliver and set it in place, pour the lid, bolt steel plates and then install the flap gate when it arrives. INDOT must approve the change order before ordering the box.