Alpena awards $248,375 green stormwater project, leveraging $115,000 grant
Summary
Council awarded Phase 1 of a green stormwater infrastructure project to MacArthur Construction for $248,375.10, with a $115,000 grant from the National Fish and Wildlife Foundation and city match from local street and public-works line items; staff said planting is expected around Oct. 1.
Get email alerts on the Stormwater Infrastructure topic
No spam. Unsubscribe anytime.
City engineer Steven Shields presented bids for the green stormwater infrastructure Phase 1 project and said two local contractors submitted proposals. Huron Pines secured a National Fish and Wildlife Foundation grant that provides $115,000 toward construction; the city will match the remaining cost from existing local-streets and public-works budgets. Staff recommended awarding the project to MacArthur Construction and council approved the $248,375.10 contract.
Shields said the work includes reconstruction of a parking lot at Third and River and a green bump-out at the DDA building on Old Washington and Chisholm; the contractor will perform site preparation and the planting window is anticipated to be around Oct. 1 when the planting partners will install vegetation. Council noted the project’s tie to the city’s “Lake Huron Forever” and related environmental commitments.