Superintendent warns kindergarten wing roof costs have risen by about $30,000
Summary
Superintendent Brenda Donahue told the board the kindergarten wing roof project increased by over $30,000 because of insulation and permitting, and said that rising costs were a principal reason the budget was placed on display.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
Superintendent Brenda Donahue told the Marseilles ESD 150 board on May 22 that the district’s kindergarten wing roof project has become more expensive.
"The cost has increased by over $30,000 due to insulation and permitting, for example," Donahue said, and she identified the higher estimate as a key reason the fiscal-year budget was included for public display that evening. No additional contractor bids or revised total project amount were presented at the meeting.