Board approves up to $525,000 BF&S engineering agreement for proposed data center; developer to contribute $35,000

City of Hobart Sanitary District/Storm Water Board ยท June 23, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The board approved a reimbursable preliminary engineering agreement with BF&S for the proposed data center not to exceed $525,000; the developer will add $35,000 via building permit fees toward the engineering cost.

The Hobart Sanitary District voted to approve a preliminary engineering agreement with BF&S for work related to a proposed data center, with the agreement capped at $525,000 and structured as reimbursable. City Engineer Alex Metz said the developer will contribute an additional $35,000 through building permit fees toward total engineering costs.

"The agreement is structured as a reimbursable arrangement, with the developer contributing an additional $35,000 through building permit fees toward the total engineering cost of $525,000," Metz said. Mr. Larry Gutierrez moved to approve the BF&S agreement not to exceed $525,000; the motion was seconded and carried (4/0). The approval maintains project momentum while finalizing the Sanitary Service Connection Agreement and related reimbursements.