Long Prairie council approves $32,280 change order to pave Riverside Drive drainage swale
Summary
The council approved Change Order No. 11 to pave a repeatedly eroding drainage swale on Riverside Drive at a quoted $32,280, with Todd County paying 56% ($18,076.80) and the City 44% ($14,203.20). The measure passed unanimously.
Get email alerts on the Infrastructure Drainage topic
No spam. Unsubscribe anytime.
The Long Prairie City Council on Aug. 27 approved Change Order No. 11 to pave a drainage swale on Riverside Drive after engineers concluded ongoing erosion problems required a hard-surface solution. City Engineer Kent Louwagie told the council the drainage swale carries runoff from roughly 70 acres and that "the best available solution is to pave the drainage swale." The contractor's quote for the work is $32,280, with Todd County responsible for 56% ($18,076.80) and the City of Long Prairie covering 44% ($14,203.20).
Council Member Lilah Gripne moved approval; Council Member Gabrier Perez seconded and the motion was adopted unanimously. The change order extends the project closeout date to Nov. 1 to allow time for the work and financing to be completed. The council record shows the action was taken as a formal contract modification tied to the CSAH 56/38 project coordination described by the city engineer.