Summary

Council approved pay application #3 and change order #3 for the Capital Avenue project to Eminent Contracting, noting the change order was negative and the project is under budget and now 100% complete.

Director Kimberly Maroney presented pay application number 3 and change order number 3 for Eminent Contracting, LLC for the Capital Avenue project: pay application $145,147.94 and change order −$176,516.03. Maroney said the net effect balanced the project and that the work is now 100% complete.

Council moved to approve the pay application; the roll call vote carried. Council members praised the under‑budget outcome and thanked staff and contractors for completing the project.

AI generated

The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.

AI can make mistakes, so if you spot one, and we will fix it for everyone.

Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.

Source