Council approved pay application #3 and change order #3 for the Capital Avenue project to Eminent Contracting, noting the change order was negative and the project is under budget and now 100% complete.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
Director Kimberly Maroney presented pay application number 3 and change order number 3 for Eminent Contracting, LLC for the Capital Avenue project: pay application $145,147.94 and change order −$176,516.03. Maroney said the net effect balanced the project and that the work is now 100% complete.
Council moved to approve the pay application; the roll call vote carried. Council members praised the under‑budget outcome and thanked staff and contractors for completing the project.