Playground renovation at Thomas delayed; shade structure and equipment now due in August
Summary
District staff reported demolition began July 7 but soil compaction issues have delayed the Thomas playground; shade structure ships Aug. 18 and equipment Aug. 25, with architects and contractors scheduled to discuss alternatives.
Get email alerts on the Facilities Playground topic
No spam. Unsubscribe anytime.
Carbondale ESD 95 staff reported the Thomas playground demolition began July 7 but that unexpected soil compaction issues have delayed completion originally estimated for July 25.
Chief School Business Official Janiece Blake said a meeting with W&B Architects, Samron, Klingner & Associates, Hutchinson Recreation and district representatives was held to address the issue. Blake reported the shade structure has a ship date of Aug. 18 and the equipment a ship date of Aug. 25; staff flagged recess alternatives until the site is ready and noted Sesser Pave and Seal will reseal and stripe the asphalt surface after installation.