District Advances Playground Renovation Planning; Hires Surveyor for $6,350
Summary
The Building & Transportation Committee reported hiring Klingner & Associates to survey and produce civil design for playground and soccer field regrading and drainage at Thomas School for $6,350, with target completion May 1.
Get email alerts on the Playground Renovation topic
No spam. Unsubscribe anytime.
The board's Building and Transportation Committee reported that the district will hire Klingner & Associates to survey the playground and soccer field at Thomas School and produce civil designs addressing regrading and drainage relief. The committee presented a $6,350 scope of work and a target completion date of May 1.
Chief School Business Official Janiece Blake said the district is using the Sourcewell purchasing cooperative to streamline procurement from approved manufacturers and dealers once design decisions are finalized. The committee report said the district is developing design options and will order equipment after site work is complete so installation can proceed promptly.
No separate board action approving equipment purchase was recorded at the April 24 meeting; the entry in committee reports documents the recommendation and next steps for site survey and design work.