Board places up to $25,000 in SPLOST funds on consent for PSC roof change orders
Summary
Contractors replacing the Public Safety Complex roof found deteriorated plastic gas‑line supports and proposed a $12,800 change order to replace supports and paint the gas line. Staff recommended approval and asked the Board to place up to $25,000 in SPLOST funds on the consent agenda to cover this and any further engineer‑recommended change orders.
Get email alerts on the Public Works topic
No spam. Unsubscribe anytime.
The Board reviewed ongoing work at the Public Safety Complex roof replacement project, which was previously authorized for $689,910 in SPLOST funds. Contractors reported that plastic gas‑line supports are breaking from prolonged sun exposure and submitted a $12,800 change order to replace the supports and paint the gas line to prevent corrosion and staining. Aaron Wadley advised the Board that the proposed cost was fair and recommended approval.
Staff requested the Board place on the consent agenda approval of up to $25,000 in SPLOST funds to cover the current change order and any additional change orders recommended by the engineer and approved by the County Manager. Commissioner Nathan Park moved to place the item on the consent agenda; Commissioner Carl Jones seconded the motion, which was recorded in the minutes for later consent‑agenda action.