Committee moves to close out emergency bypass support project Phase 2 with change order

Sunnyside-Tahoe City Sewer & Water Committee · December 12, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Philip Tapia told the committee the emergency bypass support project (Phase 2) is complete and a change order is needed to balance quantities and cover additional paving, BMP work and vault modifications; staff recommended approval on consent despite the final contract exceeding the original board-approved amount plus contingency.

Philip Tapia, construction manager, briefed the committee on Contract Change Order No. 2 to close out Phase 2 of the emergency bypass support project. "The project is complete. We finished this past fall with successful completion," he said, and described additional paving, BMP work and vault modifications included in the change order.

Philip told the committee the project is within the 2024 budgeted amount but exceeded the board-approved construction contract amount (including the 10% contingency), which is why staff brought the change order forward for committee approval on consent. Staff recommended placing the item on the consent agenda; the chair confirmed consent with no roll-call vote recorded in the transcript.