WEM superintendent reports Phase 2 demolition complete as district finishes one-site transition

Waterville-Elysian-Morristown Board of Education · June 22, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Superintendent Mark Winter told trustees that Phase 2 demolition is mostly finished, Morristown is 95% cleared and the district is officially on one site in Waterville; board adopted the 10-year LTFM plan tied to facilities work.

Superintendent Mark Winter updated the Waterville-Elysian-Morristown Board that Phase 2 of construction is progressing on schedule and that the district is "officially on one-site," with Morristown 95% cleared out.

Administrators described a concentrated effort over the final school days to move Morristown operations into Waterville, with elementary staff also performing heavy unpacking and classroom setup during workshop week. Trustees approved the district's Fiscal Year 10 Long-Term Facilities Maintenance (LTFM) Ten-Year Plan and discussed budget and timeline alignment with ongoing demolition and indoor air quality project payments.

Board members indicated the timeline and budget remain on schedule; staff were directed to continue implementation per the LTFM plan and to report back on any changes that could affect the preliminary budget.