Board hears updates on playground delivery and Lewis modular utilities
Summary
Chief School Business Official Janiece Blake reported Thomas playground equipment delivery scheduled for Aug. 29, work needed on site prep and Lewis modular utilities progressing; students expected to occupy the modular within a few weeks.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
Janiece Blake told the board that Thomas School playground equipment was scheduled to be delivered Aug. 29 and that Hutchinson Recreation had identified several contractor items to finish before turf and equipment installation could begin. Blake said contractors were scheduled to complete the corrective items early the following week so equipment installation could proceed.
Blake also reported the Lewis modular is on site and crews are working to get utilities operational; district staff expect students will be able to occupy the modular within the next couple of weeks. Resource center work at Parrish and Carbondale Middle School was also scheduled to begin in the next few weeks, though longer lead times for playground equipment may affect future schedules.