Commission awards concrete contract for generator 'cap' project to low bidder
Summary
Commissioners approved a low bid to furnish concrete work for the generator cap and control house project; bids ranged from about $183,883 to $274,240, and staff said the low bidder will provide a performance bond and crews plan to pour concrete by Oct. 1.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
Jamie Huber, speaking for the electrical/capital project team, reviewed three sealed bids for the concrete work tied to the generator cap and control house. He said the lowest responsive bid was $183,883 and that the contractor would provide a performance bond because the work exceeds $100,000.
Huber said crews hope to start mid-September with concrete poured by Oct. 1 to allow at least a month of curing before cast components arrive around Nov. 1. A commissioner moved to award the contract to the low bidder and the commission approved the award by voice vote. Staff will complete bonding and scheduling and expect work to proceed this fall.