City: Army Corps letter expired, Army Corps/other approvals tied to bulkhead permit not demolition
Summary
Planning staff told attendees the Army Corps authorization on file is expired and that Army Corps/Dept. of Fish & Wildlife and regional water board approvals are conditions for the bulkhead permit (not the demolition permit); Army Corps status is listed as pending.
Get email alerts on the Agency Approval topic
No spam. Unsubscribe anytime.
Staff told the public that Condition 11 requires approvals from the Regional Water Quality Control Board, the California Department of Fish and Wildlife and the U.S. Army Corps of Engineers before issuance of any building permit tied to the bulkhead, and that those agency authorizations are being tracked as part of the bulkhead permit process.
"The army corps of engineer letter is expired. So we have this 1 in our table as pending," Rebecca Markwick said. Staff said they have communicated to the applicant that an updated Army Corps letter is required during the 60‑day window and that the bulkhead permit is tied to the regulatory agencies' approvals; the bulkhead permit must be issued before demolition can commence.
The building official and city engineer explained that certain dates in the applicant's construction schedule were set to align with agency windows, and that if regulatory agencies extend allowed work dates the city will follow suit. Residents and BLPOA pressed staff about whether agencies had received amended plans; staff said some agency letters are on file but others await updated submittals.