Highland High bid far above estimates; district negotiates to reduce gap

Salt Lake City School District Board of Education · August 4, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Construction bids for Highland High came in roughly $25M over the estimate; administrators said negotiated value‑engineering has reduced the gap to about $17M and identified scope adjustments (skylights, tile sizes) and timeline options for ground‑source heat pump work.

The Salt Lake City School District construction manager told the board Aug. 4 that Highland High School's contractor bid came in about $25 million over the project's original estimate. District and contractor negotiations trimmed the overage, and staff reported the latest projection is roughly $17 million above the initial budget estimate.

Program manager Isaac Gastel said the reductions were achieved through scope and specification adjustments — for example, using different skylight sizes and a standardized tile finish rather than lower quality finishes. He highlighted one major driver: a ground‑source heat pump component that, when the project schedule was shortened to avoid removing baseball/softball fields for more than a season, increased that portion of the bid by about $22 million compared with earlier preliminary estimates. Gastel said some schedule flexibility (an extra season and a half) could reduce that line item by roughly $2 million.

"The bid came in just under $25,000,000 over budget for Highland High School," Gastel told trustees, adding that changes to finishes and timing have brought the overage down to around $17,000,000. Trustees asked for clarity about when taxpayers will begin to pay bond tranches and how additional tranches will affect future tax rates; finance staff said the district sold the first roughly $140 million tranche in spring 2025 and taxpayers are currently paying on that tranche.