AG|CM says 2025 Bond projects on schedule; overall completion expected Spring 2028
Summary
AG|CM representatives told the Wimberley ISD Board that Blue Hole parking, WHS and DJH improvements, roofing and HVAC projects, and Texan Stadium enhancements are progressing as planned and that overall bond-program completion is anticipated in Spring 2028.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
Representatives from AG|CM updated trustees May 18 on the 2025 Bond Program. They reported progress on the Blue Hole parking project, improvements at Wimberley High School and Danforth Junior High, roofing and HVAC work, and enhancements at Texan Stadium.
AG|CM said projects continue to progress on schedule, additional construction activities are planned for Summer 2026, and overall completion is anticipated in Spring 2028. The minutes do not list project-specific budget adjustments or contractor cost changes in the public record.
AI generated
The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.
AI can make mistakes, so if you spot one, and we will fix it for everyone.
Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.