Wimberley ISD board approves GMP #2 for high-school, junior-high, stadium and multipurpose center work

Wimberley Independent School District Board of Trustees · April 20, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Trustees approved Guaranteed Maximum Price #2 with Bartlett Cocke to continue construction at Wimberley High School, Danforth Junior High, Texan Stadium and the Shaded Multipurpose Activity Center, delegating final execution to the superintendent; the bond program remains on schedule through Spring 2028.

The Wimberley Independent School District Board of Trustees on April 20 approved Guaranteed Maximum Price (GMP) Amendment #2 with Bartlett Cocke to advance additions and renovations at Wimberley High School, Danforth Junior High, Texan Stadium and the Shaded Multipurpose Activity Center.

"I move that the Board approve the Guaranteed Maximum Price #2 with Bartlett Cocke for the Wimberley High School Additions/Renovations, Danforth JHS Additions/Renovations, Texan Stadium Additions/Renovations and the Shaded Multipurpose Activity Center Project as presented by Administration, and further delegate authority to the Superintendent to finalize any negotiations related to the Guaranteed Maximum Price (GMP) Amendment #2 and execute the GMP Amendment in a form approved by legal counsel," Trustee Lindsey Deringer moved; the motion was seconded by Dr. Rob Campbell and passed unanimously among those present (Yea:5, Nay:0, Absent:2).

Representatives from AG|CM, Inc. and O'Connell Robertson — Mark Johnson, Ryan Rosborough and Rachel Toronjo — briefed the board before the vote. They said work across multiple bid packages (site work, roofing, HVAC and campus improvements) is tracking within budget and that the overall 2025 Bond Program is scheduled for completion through Spring 2028. The board delegated authority to the superintendent to complete final negotiations and execute the GMP amendment in a form approved by legal counsel.