Board approves final change orders for CDBG and MFT projects totaling about $180,779
Summary
Trustees approved final balancing change orders including a $156,402 increase on the Roundgate CDBG subdivision project (revised contract $2,056,402.40) and a $24,377 increase for the 2024 MFT pavement patching program (revised final $213,863.50).
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
Public Works staff presented two final balancing change orders for completed infrastructure work. For the Roundgate Subdivision CDBG project, staff recommended approving an increase of $156,402.40 to cover unforeseen field conditions (underground storage tanks, additional restoration and utility adjustments), bringing the final contract to $2,056,402.40.
For the 2024 MFT pavement patching program, staff described additional patches added by direction that increased the contract by $24,377, resulting in a revised final amount of $213,863.50; staff said they will return early in the year with a final MFT resolution to reconcile allocations after the board approved the change order.