Highway superintendent reports Buck Road complete; truck estimate about $300,000

Madrid Town Board · October 9, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Highway Superintendent Bill Barkley told the Madrid Town Board that the Buck Road project is complete and that the department priced a second new truck at approximately $300,000; he also interviewed a potential new employee.

Highway Superintendent Bill Barkley reported multiple operations items at the Oct. 9 Madrid Town Board meeting.

Barkley told the board that the Buck Road project is complete. The minutes also record that Barkley interviewed a potential new employee and that the department priced a second new truck at about $300,000. The truck price was entered in the meeting record as "approximately $300,000.00." The board did not attach funding or procurement instructions to the truck note in the minutes.

No formal vote or personnel action was taken in open session; the items were entered as departmental updates.