Highway superintendent reports Buck Road complete; truck estimate about $300,000
Summary
Highway Superintendent Bill Barkley told the Madrid Town Board that the Buck Road project is complete and that the department priced a second new truck at approximately $300,000; he also interviewed a potential new employee.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
Highway Superintendent Bill Barkley reported multiple operations items at the Oct. 9 Madrid Town Board meeting.
Barkley told the board that the Buck Road project is complete. The minutes also record that Barkley interviewed a potential new employee and that the department priced a second new truck at about $300,000. The truck price was entered in the meeting record as "approximately $300,000.00." The board did not attach funding or procurement instructions to the truck note in the minutes.
No formal vote or personnel action was taken in open session; the items were entered as departmental updates.