Facilities director reports well-replacement cost spike; state requires well destruction

Loma Prieta Joint Union Elementary School District Board of Trustees · November 14, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Facilities staff told trustees the well replacement bid came in at about $815,000—roughly 30% above prior estimates—and the State Water Board is asking the district to destroy two older wells, which could add up to roughly $150,000 per well to the project.

Facilities staff provided a multi-part update on the district’s well-replacement and related projects. The well replacement bid returned substantially higher than earlier estimates, and the state has required additional remediation work on older wells tied to contamination concerns. The district is preparing follow-up materials for the State Water Board and expects to present updated cost details to the board soon.

Paul Hartle, the district’s project lead, said the current project estimate is about $815,000 and described additional tasks the State Water Board has requested. “The amount's 815,000,” Hartle said. He told trustees the board asked for detailed answers and the district expects a follow-up call with the state to present the full package of information. Hartle also described a required well-destruction process for older contaminated wells, saying, “We actually will have to send down a small explosive,” and explained that properly sealing the old well could add substantial cost to the overall project.