CESA 10 says Phase 2 of Boyceville referendum will start June 1; village approved bus garage variance

Boyceville Community School District Board of Education · May 20, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Alex Larson of CESA 10 told the Boyceville Board that Phase 2 construction will begin June 1 and outlined remaining projects, while Superintendent Nick Kaiser said irrigation for the TCE practice field will be covered by the maintenance budget rather than referendum funds.

The Boyceville Community School District Board on May 20 heard an update from Alex Larson of CESA 10 on the district’s referendum projects, with Phase 2 work slated to start June 1.

Larson said Phase 1 items are complete except for a few warranty issues and that Phase 2 will include “TCE gym flooring, hallway flooring, tech ed remodel, and locker refinishing and replacement.” He added that the bus garage canopy design is progressing after the village approved a site variance on April 28, 2026, and that outstanding items include the middle school gym floor, irrigation for ball fields, bleacher updates, and site concrete fixes.

Superintendent Nick Kaiser clarified the budgetary split for one pending item: the district will fund irrigation for the TCE practice football field from its maintenance budget rather than the referendum fund. The construction schedule and room closures were described as likely to affect summer school location planning and access to classrooms during the summer work.

Why it matters: the Phase 2 schedule affects building access and summer programming and determines which projects are paid from referendum proceeds versus district maintenance funds.