Subcommittee favors bridge-mounted pipe hangers and bid alternates over extensive directional drilling
Summary
Stantec and committee members favored attaching the force main to existing bridge hangers to avoid directional drilling under creeks, and recommended including trenchless bid alternates where appropriate to give the district permitting and cost flexibility.
Get email alerts on the Construction Permitting topic
No spam. Unsubscribe anytime.
Stantec told the subcommittee its field work found space to hang a pipeline on the downstream side of several bridges rather than relying on directional drilling under creeks. Carrie Poytruss said bridge-mounted hangers and HDPE pipe reduce drilling-fluid permitting concerns and allow visible inspection; committee members and a county bridge engineer expressed support for that approach as a 30%-design assumption.
Stantec also recommended including directional-drill or HDD bid alternates for specific pipeline stretches where HDD is feasible; the firm said 6-inch HDPE bores under 1,000 feet are commonly practical depending on contractor capability. Members asked that the report note permitting tradeoffs and include a paragraph describing why bridges were preferred for this stage of design.