Committee hears Solvang upgrade could require $3.5M of pipe work before a Los Olivos connection
Summary
District staff said City of Solvang engineers identified about $3.5 million in pipe upgrades needed in Solvang’s system; Stantec and the subcommittee said Solvang’s funding and schedule are the critical external constraints for any connection, potentially delaying action until after Solvang secures its funding.
Get email alerts on the Municipal Funding topic
No spam. Unsubscribe anytime.
Guy Savage, the district’s general manager, briefed the subcommittee on a recent meeting with Solvang staff and consultants. Savage said the City’s consultants (Corello and WSC in prior studies) identified roughly $3,500,000 in pipe and pump upgrades that should be completed for a reliable connection and that Solvang will not return to its council until funding for its upgrade project is secured.
Subcommittee members said those Solvang CIPs (capital improvement projects) are a primary external constraint on the district’s schedule and recommended the 30% design assume the city’s improvements are in place. Stantec reiterated that its conceptual design assumes Solvang implements the identified CIPs; the firm noted its modeling stretches timing windows for sending flow if those CIPs are completed.