Florence board approves $92,728.14 final pay request to Thornton Construction for College Street pump station force main
Summary
The board approved Pay Request #2-final to Thornton Construction Company, Inc. for $92,728.14 for the Florence College Street Pump Station Force Main Replacement Project on motion from Alderman John Banks.
Get email alerts on the Infrastructure Payment topic
No spam. Unsubscribe anytime.
City Engineer Tim Parker recommended approval of Pay Request #2-final payable to Thornton Construction Company, Inc. in the amount of $92,728.14 for the MCWI#255-2-CW-5-5 Florence College Street Pump Station Force Main Replacement Project. Alderman John Banks moved the payment, Alderman Brian Grantham seconded, and the board carried the motion by unanimous vote of members present.
The minutes record the project identifier and final pay amount; they also record that Alderman Mason Herrin had briefly left the meeting and returned without participating in that vote. The minutes do not include contractor comment or additional change-order detail.