Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Ev Charging topic
No spam. Unsubscribe anytime.
Commission backs MG&E proposal to install DC fast chargers at Lakeview Park
Summary
The commission approved a staff recommendation to host four MG&E Level‑3 DC fast chargers at Lakeview Park parking lot; MG&E will operate and maintain chargers for five years and drivers pay electricity fees, with options at five years for the city to take ownership or have removal/restoration.
Get email alerts on the Ev Charging topic
No spam. Unsubscribe anytime.
The commission voted to support MG&E's proposal to install Level‑3 DC fast charging stations in the main parking lot at Lakeview Park, approving the scope presented by MG&E and asking for tree protection per city specifications.
"This item is about installing level 3 charging, which is the fast DC electric vehicle charging stations in Lakeview Park in the main parking lot," Kelly Hilliard, the city's sustainability coordinator, said as she introduced the proposal. MG&E representative Guy described site logistics — bored conduit under the lot, a transformer location, and a small trench area adjacent to the chargers — and said MG&E would operate and maintain the equipment for the first five years. "For the 1st 5 years, we do all operation and maintenance," Guy said.
Commissioners asked about user data, maintenance costs and effects on park amenities. Guy said drivers pay for electricity at the charger and that the host entity bears no electricity cost while MG&E operates it; he added the chosen chargers have strong reliability records and were expected to last well beyond five years. On data, Guy said the operator can provide usage statistics (kilowatt-hours, counts of charges, and percent use) but not identifying information because of privacy policies.
The commission also discussed placement concerns — the transformer may partially block a park sign — and tree‑protection requirements; staff noted a planned future adjustment of park signage and sidewalks as part of capital improvements. The commission approved the recommendation to have MG&E host the chargers and directed staff to include tree protection in site work.

