River Ridge board ratifies $150,786 change order for stormwater work amid member objections
Summary
The board ratified MRI Construction Change Order Estimate #500 for $150,786.09 to alter Phase I/II stormwater inlets after field changes; one supervisor criticized the timing and cumulative overrun and counsel was directed to draft approval 'ground rules' for large projects.
Get email alerts on the Procurement topic
No spam. Unsubscribe anytime.
District Engineer Charlie Krebs and PSGRC General Manager Eric Long explained that relocating inlets for Phase II was necessary after touring the site with homeowners and reviewing existing conditions. Mr. Blumenthal and Mr. Long said the end result will function to eliminate standing water; staff described the change as needed given field conditions.
Vice Chair Terry Mountford objected to the process, stating the CDD "was already $300,000+ over budget for this type of project" and that approving "another $150,786.09 expense without scheduling a Special Meeting to discuss and vote on it is not being fiscally responsible." The board discussed building contingency amounts into future projects and setting policy authorizing a project manager to approve amounts within a contingency threshold. District Counsel Tony Pires was directed to draft 'ground rules' for approvals on large projects.
On motion by Mr. Blumenthal and seconded by Mr. Merrill, with all in favor, MRI Construction, Inc. Change Order Estimate #500 for Price Changes of Phase I and Phase II Stormwater Management Projects in the amount of $150,786.09 was ratified. The board recorded no opposing votes.