Town hears timeline for National Grid Raquette Lake substation work starting March 3

Town Board of Long Lake · February 26, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Supervisor Arsenault told the board a National Grid preconstruction meeting is scheduled March 3 in Raquette Lake; civil work will occur through March, overhead line work in April, underground work in May, with the old substation retired and site restored by July or August.

Supervisor Clay J. Arsenault told the board the Town received a construction schedule from National Grid for the Raquette Lake substation project.

"On March 3ʳᵈ there will be a preconstruction meeting on site, and through the month of March civil work will be conducted at the new site. In April the overhead line work will begin, with wooden poles being placed within the new location, eventually new poles will be placed along Route 28. In May underground work is scheduled within the footprint of the new site. By July or August, the old substation will be retired and the site cleaned up with everything removed and grass planted," Arsenault said. The board received the schedule as informational; no vote was taken.