County engineer reports culvert, graveling and bridge applications; flags $6K–$8K change order

Chickasaw County Board of Supervisors · August 4, 2026

Summary

An engineering update detailed graveling and patching on multiple county roads, culvert work north of Lawler, and a bridge permit application to FHWA with an estimated announcement date of Sept. 14. The speaker flagged a likely $6,000–$8,000 change order for north pier excavation.

Roman Lutsky, county engineer, provided a progress report on county road and bridge work, saying crews completed about half of the best route and placed a culvert on B46 north of Lawler with the aim of reopening that road segment. He described ongoing work on B33 and spot blading across the northeast corner of the county.

"We did place the culvert on B 46 North of the Lawler. Hopefully, get that opened up today," the speaker said. He added that many patches would be graveled "until roughly September, October when we fill them with HMA."

The engineer also said the north pier on a bridge project required an additional foot of excavation into bedrock and that the extra work would likely produce a change order in the range of $6,000 to $8,000. He reported the county submitted the 2026 highway bridge program application to the Federal Highway Administration on July 24 and cited Sept. 14 as the estimated announcement date for that grant program.

AI generated

The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.

AI can make mistakes, so if you spot one, and we will fix it for everyone.

Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.

Source