Applicant details siting, wiring, monitoring and construction timeline for Cortland solar project

Town of Cortland Planning Commission · April 2, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

SolarStone Partners told the Planning Commission panels would occupy about 37 acres, use underground wiring to the transformer, include vegetative screening outside the fence, and be monitored remotely; the applicant estimated a six- to 12-month construction timeline.

At the April 2 hearing, applicant Josh Marshall outlined technical and design elements for the proposed Cortland solar garden, saying about 37 acres of the 80.33-acre parcel would host panels and wiring would be buried to the transformer. Marshall said subscriptions for the facility would typically offer a 15–20% discount to subscribers, and that monitoring systems would track panel performance and weather conditions.

Marshall also described planned screening and fencing: screening plantings would sit outside an ag woven-wire fence and no barbed wire would be used. On maintenance and safety, he cited TCLP/EPA guidance and said modern panels are "non-hazardous for modern solar panels." He estimated construction could be completed in a six-to-12-month timeframe and said remote monitoring allows operators to identify and repair panel issues in hours to days.