Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Capital Projects topic

No spam. Unsubscribe anytime.

Geothermal HVAC work under way at Dunn County Judicial Center; drilling to start in weeks

Dunn County Facilities Committee · August 5, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Facilities staff told the committee the geothermal HVAC RFP for the Judicial Center was issued last November, that on-site work started the day of the meeting, and that drilling in the geothermal field is expected in 6–8 weeks with a contractor aiming to finish in roughly nine months.

Facilities staff reported that the Judicial Center geothermal HVAC project, long in planning, has progressed to on-site work.

The staff member said the RFP for the geothermal HVAC was released late last November and that "the judicial center HVAC started today," adding that project activity will be relatively quiet the first week and will ramp up next Monday. Drilling in the geothermal field is expected in about 6–8 weeks, and the contractor’s schedule was described as targeting completion in roughly nine months.

Staff added that weekly coordination meetings with affected departments would be held on Thursday mornings to monitor schedule and staging, and that certain parking areas will be blocked for equipment and crew staging while the work continues.