District awards Lincoln courtyard water relocation bid to D. Kersey Construction for $448,200
Summary
The Board awarded the Lincoln Courtyard Water Relocation contract to D. Kersey Construction for $448,200; the district engineer's estimate was $320,000 and the bid includes a $150,000 landscaping allowance.
Get email alerts on the Facilities Contracts topic
No spam. Unsubscribe anytime.
The Board awarded the Lincoln Courtyard Water Relocation contract to apparent low bidder D. Kersey Construction for $448,200, including performance bond. Chief Operations Officer Anthony Cozzi presented three bids (D. Kersey Construction $448,200; Paul Borg Construction $477,400; Charpie Construction $480,000) and noted the district contracted civil engineer’s estimate was $320,000. Cozzi said contractors attributed overages to difficulty finding subcontractors and economic uncertainty.
The contract scope includes a $150,000 landscaping allowance; Cozzi said the district will attempt to minimize landscaping costs and defer lower-priority summer projects to offset the overage. The motion to award the bid passed unanimously on roll call.